About Us General Contracting Residential Contracting Single-Ply Roofing Portfolio Contact Us
 


Portfolio

Hudson School District

1401 Vine Street
Hudson, Wisconsin 54016
715-386-4911

 

Project Description

In 2000, Wayne Nasi Construction installed 35,000 square feet of Duro-Last roofing system on three different schools. In 2003, 12,000 square feet was installed on the high school and another 21,000 square feet in 2004. Over 35,000 square feet was installed on the high school in the summer of 2005. Totaling over 103,000 square feet of the Duro-Last roofing system for the Hudson School District.

Reference

". Wayne Nasi Construction was prompt, courteous, and professional. The roofing job was completed satisfactorily. We are very happy with our Duro-Last roofing system and Wayne Nasi Construction. We would recommend them to anyone else with roofing needs."

Jim Stejskal
Supervisor of Buildings & Grounds